Module D rules
Mandatory
Required: must be met for the credential.
Klar Cite summary
Module D must have a scenario for each C3 or C4 scenario, count net recovered flows, and credit or charge average market substitutes, not marginal data.
International EPD System·clause not recorded·pp.40-41
Circular Economy · Climate Health
- Limit
- ≥ 3 years
Original wording
The publisher lets each reader see 20 of this document’s clauses a day when signed in, or 5 without signing in.
This is the publisher’s condition for Klar Cite showing its words; the limits, the citation and everything else on this page are free to read. Showing the wording counts one clause.
Details
What the product must meet
Limits held for this clause
| Parameter / context | Operator | Limit | Unit |
|---|---|---|---|
| duration | ≥ | 3 | years |
Compare this limit across schemes
The limit was read from the clause wording.
How it is proven
- Who checks it
- Independent body verifies — a certifier, auditor or verifier with no stake
Klar Cite’s reading
Klar Cite’s reading of the clause, not the scheme’s own claim.
- Type of requirement
- Check suppliers or materials — verify suppliers, documents or substances against a list or rule
- Standing
- Required — must be met for the credential
- Topic
- Circular Economy — the topic the clause addresses, grouped by the Common Materials Framework (CMF)
- Also relevant to
- Climate Health — other topics the clause addresses
- Refers to
- Annex D — places elsewhere in the document
Cite this clause
International EPD System · PCR 2019:14 Construction products · version v2.0.1 · clause not recorded · page 40-41 · build 2026-10-27-1239 · https://klarcite.com/r/b2b89b8458803109
Record details
Page 40-41, CONSEQUENCES FOR RECOVERED MATERIAL/ENERGY BEYOND THE PRODUCT LIFE CYCLE (MODULE. Read in build 2026-10-27-1239, harvested 2026-10-27.