Electricity peak demand reduction
Klar Cite’s nameMandatory
Required: must be met for the credential.
Guidance
This is guidance, not a requirement. Green Star Buildings Submission Guidelines restates what Green Star’s standard requires; the register holds it and cites it, and does not count it as a requirement or show it as one.
Superseded
The document this clause was read from is superseded. It is kept so older citations resolve.
Green Star·clause Active Generation and Storage Systems·p.132
Climate Health
- Level
- Credit Achievement
Original wording
Green Star Buildings Submission Guidelines clause Active Generation and Storage Systems — words not shown. Read it at the source. The held copy is a single-user licence and does not extend to republishing its clauses.
The clause is held and verified. Only its words are withheld.
Klar Cite classification — not the standard’s words
Addresses: building's capacity to reduce peak demand
written by a model, checked against the clause
Details
How it is proven
- Who checks it
- Independent body verifies — a certifier, auditor or verifier with no stake
Klar Cite’s reading
Klar Cite’s reading of the clause, not the scheme’s own claim.
- Type of requirement
- Meet a limit or condition — e.g. a maximum emission or a minimum recycled content
- Standing
- Required — must be met for the credential
- Topic
- Climate Health — the topic the clause addresses, grouped by the Common Materials Framework (CMF)
- Level
- Credit Achievement — the level of the credential this clause belongs to
Cite this clause
Green Star · Green Star Buildings Submission Guidelines · version v1 Rev C · clause Active Generation and Storage Systems · page 132 · build 2026-10-27-1239 · https://klarcite.com/r/e624c7c25c84e232
Record details
Page 132. Read in build 2026-10-27-1239, harvested 2026-10-27.
uid e624c7c25c84e232 · document 51b013d0b927654f · fidelity verbatim · published 2023-10