Recycled water readiness
Klar Cite’s nameMandatory
Required: must be met for the credential.
Guidance
This is guidance, not a requirement. Green Star Buildings Submission Guidelines restates what Green Star’s standard requires; the register holds it and cites it, and does not count it as a requirement or show it as one.
Green Star·clause Credit 28·p.230
Ecosystem Health
- Exemption
- Projects not located in areas of planned recycled water infrastructure are exempt from the Recycled Water Infrastructure criterion.
- Level
- Credit Achievement
Original wording
Green Star Buildings Submission Guidelines clause Credit 28 — words not shown. Read it at the source. The held copy is a single-user licence and does not extend to republishing its clauses.
The clause is held and verified. Only its words are withheld.
Klar Cite classification — not the standard’s words
Addresses: preparedness for recycled water systems
written by a model, checked against the clause
Details
What the product must meet
- Exemptions
- Projects not located in areas of planned recycled water infrastructure are exempt from the Recycled Water Infrastructure criterion.
How it is proven
- Who checks it
- Applicant declares — a signed statement from the applicant
Klar Cite’s reading
Klar Cite’s reading of the clause, not the scheme’s own claim.
- Type of requirement
- Provide information — e.g. declare ingredients or publish an environmental product declaration
- Standing
- Required — must be met for the credential
- Topic
- Ecosystem Health — the topic the clause addresses, grouped by the Common Materials Framework (CMF)
- Level
- Credit Achievement — the level of the credential this clause belongs to
Cite this clause
Green Star · Green Star Buildings Submission Guidelines · version v1.1 Rev A · clause Credit 28 · page 230 · build 2026-10-27-1239 · https://klarcite.com/r/785abb4e582e88bd
Record details
Page 230. Read in build 2026-10-27-1239, harvested 2026-10-27.
uid 785abb4e582e88bd · document b6cffefd9806e9f5 · fidelity verbatim · published 2025-10