Commitment to measure in-use water consumption
BREEAM·clause Wat 05 M3·p.292
The requirement
BREEAM International New Construction Technical Manual clause Wat 05 M3 — words not shown. Read it at the source. The publisher reserves the right to its wording and sells access to it. The clause is held and cited here, and its words are read at the source.
The clause is held and verified. Only its words are withheld.
How it is proven
- Evidence required
- Criteria Interim design stage Predict operational water consumption
- Who checks it
- Applicant declares — a signed statement from the applicant
How Klar Cite classifies it
Klar Cite’s reading of the clause, not the scheme’s own claim.
- What it asks
- Have in place — a plan, procedure or system the applicant must operate
- Standing
- Required — must be met for the credential
- Impact area
- Ecosystem Health — the CMF area the clause addresses
Cite this clause
BREEAM · BREEAM International New Construction Technical Manual · version v7.1 · clause Wat 05 M3 · page 292 · build 2026-10-05-0439 · https://klarcite.com/r/e2b5757954b9f795
Record details
Page 292, WAT 05 PREDICTION OF OPERATIONAL WATER CONSUMPTION. Read in build 2026-10-05-0439, harvested 2026-10-05.
uid e2b5757954b9f795 · document e3e19e8b697bf44b · fidelity verbatim · published 2024