The requirement

The publisher’s words are shown on request, below the limits.

The publisher’s words

The publisher lets each reader see 3 of this document’s clauses a day.

This is the publisher’s condition for Klar Cite showing its words; the limits, the citation and everything else on this page are free to read. Showing the wording counts one clause.

How it is proven

Evidence required
DoC EV-5.2.1: evidence that a GECA-licensed waste recovery service has been used or evidence of the segregation system signage in action onsite. DoC EV-5.2.2: evidence of the system used on site to protect material.
Who checks it
Independent body verifies — a certifier, auditor or verifier with no stake

How Klar Cite classifies it

Klar Cite’s reading of the clause, not the scheme’s own claim.

What it asks
Have in place — a plan, procedure or system the applicant must operate
Standing
Required — must be met for the credential
Impact area
Circular Economy — the CMF area the clause addresses

Cite this clause

GECA · Construction & Demolition Waste Services · version CDWS Gen 3.0 · clause EV-5.2 · page 31 · build 2026-10-05-0439 · https://klarcite.com/r/73f47d0093cbef53

Source document

Record details

Page 31, EV-5.2 PRACTICE. Read in build 2026-10-05-0439, harvested 2026-10-05.