Air contaminant source control

LEED·clause Strategy 10. Additional Source Control and Monitoring·p.119

Klar Cite’s name for this clause. The publisher’s own heading may not be shown.

The requirement

LEED v4.1 Building Design and Construction Rating System clause Strategy 10. Additional Source Control and Monitoring — words not shown. Read it at the source. The held copy is a single-user licence and does not extend to republishing its clauses.

The clause is held and verified. Only its words are withheld.

Klar Cite classification — not the standard’s words

Addresses: air contaminant sources and monitoring

written by a model, checked against the clause

Read it at the source

What the product must meet

Applies to
New Construction, Core & Shell, Schools, Retail, Data Centers, Warehouses & Distribution Centers, Hospitality, Healthcar

How it is proven

Who checks it
Independent body verifies — a certifier, auditor or verifier with no stake

How Klar Cite classifies it

Klar Cite’s reading of the clause, not the scheme’s own claim.

What it asks
Meet — a limit, condition or outcome the product must satisfy
Standing
Required — must be met for the credential
Impact area
Human Health — the CMF area the clause addresses

Cite this clause

LEED · LEED v4.1 Building Design and Construction Rating System · version v4.1 · clause Strategy 10. Additional Source Control and Monitoring · page 119 · build 2026-10-05-0439 · https://klarcite.com/r/ebd7730481615e34

Source document

Record details

Page 119. Read in build 2026-10-05-0439, harvested 2026-10-05.

uid ebd7730481615e34 · document 735b8f7d282ce93c · fidelity verbatim · published 2025-02-01