Implement water management plans with time-bound targets addressing Material risks
Klar Cite synopsis
The company must implement water management plans with time-bound targets addressing Material risks. It applies to all Facilities. This concerns ecosystems and nature.
Aluminium Stewardship Initiative·clause 7.2a·p.21
The requirement
The publisher’s words are shown on request, below the limits.
What the product must meet
- Applies to
- all Facilities
- Exemptions
- This criterion is Not Applicable where risks identified in 7.1b are assessed and documented as low.
The publisher’s words
The publisher lets each reader see 20 of this document’s clauses a day when signed in, or 5 without signing in.
This is the publisher’s condition for Klar Cite showing its words; the limits, the citation and everything else on this page are free to read. Showing the wording counts one clause.
How it is proven
- Who checks it
- Applicant declares — a signed statement from the applicant
How Klar Cite classifies it
Klar Cite’s reading of the clause, not the scheme’s own claim.
- What it asks
- Have in place — a plan, procedure or system the applicant must operate
- Standing
- Required — must be met for the credential
- Impact area
- Ecosystem Health — the CMF area the clause addresses
Cite this clause
Aluminium Stewardship Initiative · ASI Performance Standard · version V3.1 · clause 7.2a · page 21 · build 2026-10-06-0600 · https://klarcite.com/r/bfe1b2a47eacd703
Record details
Page 21, 7.2 Water Management. Read in build 2026-10-06-0600, harvested 2026-10-06.
uid bfe1b2a47eacd703 · document 2e194b162bfab131 · fidelity verbatim · published 2023-04