Set targets for demolition waste salvage and diversion
Eco Choice Aotearoa·clause 8.1(a)·p.18
The requirement
The publisher’s words are shown on request, below the limits.
What the product must meet
Limits held for this clause
| Parameter / context | Operator | Limit | Unit |
|---|---|---|---|
| The WMP prepared under 5.1(b) must include a target of more than 5 | ≤ | 5.1 | unit not recorded |
| for reuse or recycling and more than 70% of C&D waste to be diverted from dispos | ≥ | 70 | % |
How these limits relate is not stated in the document, so treat them as listed, not as a rule.
Compare this limit across schemes
The limit was read from the clause wording.
The publisher’s words
The publisher lets each reader see 4 of this document’s clauses a day.
This is the publisher’s condition for Klar Cite showing its words; the limits, the citation and everything else on this page are free to read. Showing the wording counts one clause.
How it is proven
- Who checks it
- Independent body verifies — a certifier, auditor or verifier with no stake
How Klar Cite classifies it
Klar Cite’s reading of the clause, not the scheme’s own claim.
- What it asks
- Meet — a limit, condition or outcome the product must satisfy
- Standing
- Required — must be met for the credential
- Impact area
- Circular Economy — the CMF area the clause addresses
Cite this clause
Eco Choice Aotearoa · Construction and Demolition Waste Services · version EC-59-19 · clause 8.1(a) · page 18 · build 2026-10-05-0439 · https://klarcite.com/r/2fcab18a483be5dc
Record details
Page 18, 8.1 Planning. Read in build 2026-10-05-0439, harvested 2026-10-05.
uid 2fcab18a483be5dc · document 9075746d41273f76 · fidelity verbatim · published 2023-06
Other clauses in this standard
| Clause | Name |
|---|---|
| 4.2 | Structure of specification |
| 5.1(a)(i) | Minimise C&D waste generation |
| 5.1(a)(ii) | Implement waste hierarchy |
| 5.1(a)(iii) | Engage with other service providers and waste generators |
| 5.1(b)(i) | Waste minimisation in the project waste plan |
| 5.1(b)(ii) | Waste hierarchy in the project waste plan |